English term or phrase: add one
Je n'arrive pas à comprendre ce que "add one" veut dire dans cette phrase....

"Remember that the earliest start time on the network describes the end of that day so we recommend that you add one to the earliest start time to get the actual start date."

CONTEXTE :

Having established the critical path, we can draw a Gantt chart. This will use a calendar called the project calendar and this defines which days are available for work. For example, we may only work Monday to Friday but some projects may work six days a week and use a shift system.
Firstly, draw the chart with the time units across the top and the tasks down the left hand side.
Now plot the start and finish times of each task. Remember that the earliest start time on the network describes the end of that day so we recommend that you add one to the earliest start time to get the actual start date. The end date is correctly shown on the network
Hugues Roumier
France
Local time: 22:44


Summary of answers provided
4prévoir le début un jour plus tard
Rocsana Guignaudeau


Discussion entries: 7





  

Answers


9 hrs   confidence: Answerer confidence 4/5Answerer confidence 4/5
you add one to the earliest start time to get the actual start date.
prévoir le début un jour plus tard


Explanation:
See my discussion entry and also the link mentioned in this discussion.


    https://www.edrawsoft.com/templates/pdf/develop-new-software-gantt-chart.pdf
Rocsana Guignaudeau
France
Local time: 22:44
Native speaker of: Native in RomanianRomanian
PRO pts in category: 8

Peer comments on this answer (and responses from the answerer)
agree  AllegroTrans
31 mins

disagree  Germaine: C'est le contraire: un jour plus tôt puisque chaque point "describes the end of that day so... you add one [day] to the earliest: hâter/devancer d'un jour la première date. // La prémisse y est différente; cf. le tableau de gauche.
4 hrs
  -> Je ne le vois pas comme ça. En regardant la diagramme Gannt dans le lien que j'ai marqué, les activités successives commencent l'une après la fin de l'autre mais jamais le même jour.
Login to enter a peer comment (or grade)



Login or register (free and only takes a few minutes) to participate in this question.

You will also have access to many other tools and opportunities designed for those who have language-related jobs (or are passionate about them). Participation is free and the site has a strict confidentiality policy.

KudoZ™ translation help

The KudoZ network provides a framework for translators and others to assist each other with translations or explanations of terms and short phrases.


See also:
Term search
  • All of ProZ.com
  • Term search
  • Jobs
  • Forums
  • Multiple search